Sealant replacement (all windows frame, vertical cold joints, and flashing), paint renewals at concrete wall surface, and localized concrete repairs, including exposed rebars and cracks.
Tatras Group completed the work based on the requirements of McIntosh Perry Limited, using Dymonic FC, Towerthon by Cloverdale, and Sikatop 123Plus.
Duration work: 5 months.
Pressure washing, application of urethane membrane, building envelope repairs, paint re-coating exterior concrete surfaces (wall and soffit), and localized sealant replacement.
Approach via swing stage and rope access. Work completed based on the requirements of RDH Building Science Inc, using Tremco (membrane/sealant), Cloverdale (paint) and Sika (concrete) products.
Waterproofing repairs and localized epoxy injection. We have used Tremco (pedestrian coating system), Soprema (PMMA), and Sherwin Williams (paint).
Duration: 4 weeks. It was performed under the direction of Sense Engineering.
Balcony repairs, including complex concrete repairs with exposed rebars and delaminated concrete. Membrane application on balconies and edges. Tatras Group used BASF products as liquid membrane and concrete repair mortar, as well as sika (concrete), PPG (epoxy), and Fabrikem (paint) products.
Duration: 6 weeks. It was performed under the direction of WSP Engineering.
Localized concrete repairs, sealant replacement, and exterior paint. Leak investigation and water test. Roof repairs using 2-Ply Modified Bitumen Flat Roofing Membrane System.
Duration work: 10 weeks.
Parkade membrane renewal included surface preparation, removing the failed coating on the main ramp and driveways, and membrane application using Tremco Vehicular Coating System. 20.000 SQ FT.
Duration work: 8 weeks.
Pressure washing, building envelope inspection, concrete repairs including exposed rebars, full membrane re-coating, total paint renewal at the exterior of vertical and horizontal concrete surfaces, and localized sealant replacement.
Tatras Group used Sika (concrete), Mapei (protective coating for steel reinforcing), Tremco (membrane/sealant), and Sherwin Williams (paint) products. It was performed under the direction of RDH Building Science Inc.
Pressure washing, building envelope repairs including exposed rebars and concrete cracks, full balconies and eyebrow membrane re-coating (total removal on edges), exterior wall and soffit paint re-coating. Sealer application on the outer brick surface.
Tatras Group used Tremco (membrane/sealant), Kryton (sealer) and Sherwin Williams (paint) products. It was performed under the direction of Sense Engineering.
Framing repairs, membrane replacement at all residential decks, rotten fascia boards replacement and sealant application.
We have used Sherwin Williams (paint) and Tremco(membrane) products, cedar fascia boards to provide long-lasting, DowSil sealant.
Pressure washing, envelope repairs, epoxy injection, leak investigation and full exterior re-coating. Painting all EIFS surfaces.
Material: DowSil Allguard silicone elastomeric coating.
Mortar joints removal of all inaccessible and accessible locations at the roof eyebrow.
Our crew have worked on mortar joints for building improvement during a day and night allowing all businesses and students classes operate as usual at SFU AQ Building.
Exterior siding repainting and resealing – Sealant application at all window perimeter, wood and stone cladding joint.
Tatras Group completed the work based on the requirements of Sense Engineering, using Sherwin Williams paints and Dymonic 100 sealant.
Duration work: 5 months.
Doing it right the first time.